Great question — answering as the UphillTech team:
If you are pre-sloping prior to a PVC liner, just use dry-pack. That mud base should be sitting in a depression or within a framed base. It does not need to bind to the concrete that is the foundation. However most of the time the PVC liner is laid out first and the mud base is set in that with the slope built into the Dry-pack base. I then coat the mud base and the walls with a waterproofing like RedGuard or AquaDefense. Then it is very unlikely that any water gets to the liner.
Full answer by RMDman: https://diy.stackexchange.com/a/314069 (CC BY-SA 4.0).